Bowling Green Times

Follow Us On:

Work Continues On Mississippi River Bridge

Posted on Tuesday, July 31, 2018 at 3:30 pm

By Kyle Boaz
lpjed@lcs.net

The Massman meeting had a surprise twist on Saturday, July 28.
During the presentation from Massman Project Manager Josh Hanrahan and MoDOT Senior Project Manager Keith Killen, a steel girder was placed in the background of the meeting in Henderson Riverview Park.
Workers could be heard hammering pins into place while questions were asked about the progress of the project and what the demolition would look like.
“We set the four girders on pier five and we’ll do the same thing on pier four that will make a double length segment two girders wide [and] two girders long,” Hanrahan said.
The gaps in between would be filled.
“We’ll do the same thing on pier three [by] erecting the pier girders and close the gap. So we will jump forward and then back,” Hanrahan said.
The segments of steel between the piers will be bolted together. The sections are between 70 and 80 ft. and are bolted together on the barges to make double length sections.
More steel sections should arrive late next week, according to Hanrahan.

To see the whole story pick up a copy of the Bowling Green Times at one of the following convenient locations:

BOWLING GREEN
Bowling Green Times, Abel’s Quik Shop (both locations), Ayerco Travel Plaza, Bowling Green Pharmacy, Casey’s, Crossroads, Dollar General, Save-A-Lot, Hi Rise, McDonald’s, Pike County Courthouse and Walmart

EOLIA
Fastlane and Scotty’s Citgo

FRANKFORD
Shortline 66

LOUISIANA
Abel’s Quik Shops (two locations), County Market, Green’s Family Drug and Pike County Memorial Hospital

CURRYVILLE
MeMe’s Mart & More